Permit and Design Fees Sit on Top of the Installed Cost
None of the installed-cost ranges above include what the county
charges to evaluate your site, review the design, and issue the
permit. Those fees apply no matter which installer you hire.
Here's what three Washington counties currently charge.
Thurston County: design and site-evaluation fees (2026)
Thurston prices site work separately from the permit itself:
OSS Design Review, $720; OSS
Application, $580; OSS Onsite Evaluation, $625; a Winter Water
Study, which allots 5 hours of review, $1,510; Designer Certified
Sewage Site Plan Review, $295; a Certified Water Sample, $239
($175 site visit plus $32 coliform and $32 nitrate testing). A
Winter Water Study is the kind of extra cost a high-water-table lot
can trigger before a design is even approved.
(Thurston County — 2026 Septic & CSA common fees, accessed July 22, 2026)
Thurston County permit totals, 2026
| Permit type | Total fee | What's included |
| New system: Application for Conditional Site Approval | $1,947 | OSS Application $580 + Design Review $720 + Site App Review–Planning $472 + Site App Review–Development $175 |
| Septic Construction Permit | $520 | Construction Permit $490 + O&M $30, after site approval |
| OSS Repair | $1,820 | Repair Permit App $580 + Design Review $720 + Construction Permit $490 + O&M $30 |
| Glendon Biofilter/Sand Filter/Mound Rebuild/Repair | $1,325 | Application $580 + Construction Permit $490 + O&M $30 + O&M Certificate $225 |
| Septic Tank Placement | $610 | Tank-only line item |
| Voluntary Modification of Existing System | $1,820 | |
Add $60 to a new-system application if the property sits in a
mapped flood zone or high-groundwater area. Add $225 if the system
requires an Operational Certificate, which applies to ATU, sand
filter, and mound-type systems.
(Thurston County — 2026 Septic & CSA common fees, accessed July 22, 2026)
Pierce County (Tacoma-Pierce County Health Department)
TPCHD fee schedule, 2026 adopted rates (rev. Dec 2025)
| Permit type | Fee |
| Design, Single-Family Residential (new) | $1,020 |
| Design, Single-Family Repair | $960 |
| Design, Single-Family Residential (additional residence/ADU) | $1,140 |
| Septic/Tank Repair | $360 |
| Repair, Partial | $660 |
| Installation Permit | $480 |
| Installation Permit (repair) | $480 |
| Installation Permit (tank replacement only) | $240 |
| Design, Commercial/School (1,000+ gal/day) | $1,800 |
TPCHD's design fee varies by scope: a new single-family system runs
$1,020, a repair design is $960, and a design covering an additional
residence on the same system (e.g. an ADU) is $1,140. These are the
county's Rev. 12/2025 rates, effective for 2026.
(tpchd.org — On-Site Sewage, Individual Well and Water Resources 2026 Fees, accessed July 27, 2026)
Snohomish County
Snohomish County Health Department, 2026 on-site sewage fees (selected)
| Permit type | Fee |
| Gravity Distribution, application review | $1,130 (valid 2 years) |
| Pressure Distribution, application review | $1,130 |
| All Other Systems (DOH-approved: mound, sand filter, ATU, proprietary/Glendon-type) | $1,290 |
| Product Development System (novel/pilot technology) | $1,400 base + $235/hr over 6 hrs |
| Permit for OSS, issuance (all types except community) | $385 |
| Repair (licensed designer, single-family) | $390 |
| Redesign to repair | No fee |
| Holding tank, preliminary review | $1,115 |
| Holding tank, permit fee | $640 |
| Holding tank, annual monitoring | $470 |
These figures come from the county's 2025 fee-adjustment planning
document. Snohomish's Board of Health has since finalized rates
through Ordinance BOH25-08 (effective Nov. 1, 2025) and Ordinance
BOH26-03 (2026 adjustments, approved April 14, 2026); confirm the
current line-item amount on the county's fee page before budgeting.
(snohd.org — Fee adjustment comparison, accessed July 22, 2026)
Repair costs less than new; replacement is priced like new
Washington draws a real line between "repair" and "new system,"
and it matters for your budget. WAC 246-272A-0010 defines
"repair" as relocating, replacing, or reconstructing a failed
system, or a component not on the minor-repair list, to restore
it to non-failure status. "Minor repair" covers specific damaged
components: control panels, building sewers, risers, baffles,
filters, pumps, and inspection boxes. It excludes the sewage
tank, treatment component, and soil dispersal component;
replacing any of those three counts as a full "repair" or
new-system action. A "modification" is an alteration that
doesn't expand the system, and the rule states outright that a
modification is not a repair.
(app.leg.wa.gov — WAC 246-272A-0010, accessed July 22, 2026)
The three county fee schedules above all price that distinction
the same way. Snohomish bills a full system "Replacement" at the
same rate as a brand-new application, while a "Repair" for a
single-family residence with a licensed designer's submittal is a
separate $390 line, and a "Redesign to repair" carries no fee at
all. Thurston's OSS Repair, $1,820 total, comes in cheaper than its
new-system Application for Conditional Site Approval, $1,947,
skipping the planning and development review a brand-new siting
needs; its tank-only Septic Tank Placement line is cheaper still,
at $610. Pierce County's Septic/Tank Repair, $360, and Installation
Permit (repair), $480, both undercut its Design Single-Family
Residential new-system fee of $1,020.
DOH's own consumer pages cover general maintenance and failure
signs, but don't spell out a single statewide bright line for how
repair versus replacement gets permitted. The county fee schedules
above are the clearest practical evidence of how the WAC
246-272A-0010 definitions get applied day to day; local health
jurisdictions keep some discretion, so confirm which track your
project falls under with your own county before you budget.